Putting it back together again
Thursday, December 6, 2012Posted by
Bart Treece
1 Comments
When a vital roadway gets knocked out of service, it's our job to get it back open as quickly as possible for drivers, and emergency responders. Fixing something like a bridge fixed is by no means, a small feat. An average of 15,000 vehicles each day use the northbound lanes of the SR 529 Snohomish River bridge from Everett to Marysville. This hard-working blue-collar bridge has been around for 85 years and took quite a beating this weekend when a driver smacked an SUV into a couple of support beams.
For safety, our inspectors closed the northbound bridge until the damaged support beams could be fixed. These are critical pieces that support the bridge deck. Replacement parts can't be ordered out of a catalogue, we had to custom make them from raw steel.
A team of about 30 worked in shifts around the clock to design, fabricate and install a new diagonal and vertical support beam.
After about 500 combined hours of work, the northbound SR 529 Snohomish River bridge reopened to traffic at about 12:30 p.m., Tuesday, Dec. 4. We don't roll the dice on safety. It's pretty amazing how quickly it all came together. In 81 hours, the bridge went from damaged to repaired. We closed it, stabilized it, designed replacement parts, fabricating and installed them - and only disrupting one event commute for drivers.
1 comments:
- Bridget said...
-
That's impressive turn around. I usually don't think of a gov't organization being so quick to action.
- December 7, 2012 at 12:18:00 AM PST
Subscribe to:
Post Comments (Atom)